TWINS

Project Status

CONSTRUCTION UPDATES

November 2024 Report

  • A- BLOCK
    • 17th Floor Roof Slab Completed.
  • B- BLOCK
    • 18th Floor Roof Slab Completed.
       

October 2024 Report

  • A- BLOCK
    • 15th Floor Roof Slab Completed.
  • B- BLOCK
    • 17th Floor Roof Slab Pour – 2 Completed.
       

September 2024 Report

  • A- BLOCK
    • 13th Floor Roof Slab Completed.
  • B- BLOCK
    • 15th Floor Roof Slab Completed.
       

August 2024 Report

  • A- BLOCK
    • 12th Floor Roof Slab Work In Progress.
  • B- BLOCK
    • 14th Floor Roof Slab Work In Progress.
       

June 2024 Report

  • A- BLOCK
    • 08th floor Roof Slab work in progress.
  • B- BLOCK
    • 10th floor Roof Slab work in progress.
       

May 2024 Report

  • A- BLOCK
    • 07th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 08th floor Roof Reinforcement work in progress.
       

April 2024 Report

  • A- BLOCK
    • 06th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 07th floor Roof Reinforcement work in progress.

July 2024 Report

  • A- BLOCK
    • 10th floor roof slab work in progress.
  • B- BLOCK
    • 12th floor roof slab completed.
       

June 2024 Report

  • A- BLOCK
    • 08th floor Roof Slab work in progress.
  • B- BLOCK
    • 10th floor Roof Slab work in progress.
       

May 2024 Report

  • A- BLOCK
    • 07th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 08th floor Roof Reinforcement work in progress.
       

April 2024 Report

  • A- BLOCK
    • 06th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 07th floor Roof Reinforcement work in progress.

March 2024 Report

  • A- BLOCK
    • 05th floor Roof pour- 1 work in progress
  • B- BLOCK
    • 05th floor Roof pour- 1 work in progress, pour-2 completed.

February 2024 Report

  • A- BLOCK
    • Second floor Roof slab completed.
  • B- BLOCK
    • Third floor Roof slab completed.

January 2024 Report

  • A- BLOCK
    • Second floor Roof slab work in progress.
  • B- BLOCK
    • Second floor Roof slab work in progress.

December 2023 Report

  • A- BLOCK
    • Second floor slab Reinforcement in progress.
  • B- BLOCK
    • First floor slab Reinforcement in progress.

November 2023 Report

  • A- BLOCK
    • First floor roof slab. (Transfer slab concrete casting in progress).
  • B- BLOCK
    • Second Floor Roof slab (1st Mivan slab work in progress).

October 2023 Report

  • A- BLOCK
    • First floor roof slab. (Transfer slab level work in progress).
  • B- BLOCK
    • Transfer slab Roof slab, Typical level work in progress.

September 2023 Report

  • A- BLOCK
    • First floor roof slab shuttering in progress.
  • B- BLOCK
    • Transfer slab Roof Reinforcement completed.

August 2023 Report

  • A- BLOCK
    • Clubhouse (Ground floor) slab Reinforcement work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

July 2023 Report

  • A- BLOCK
    • Ground floor walls concrete work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

June 2023 Report

  • A- BLOCK
    • Ground floor walls Reinforcement in progress.
  • B- BLOCK
    • Ground floor walls Reinforcement in progress.

May 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.

April 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab shuttering in progress.
  • B- BLOCK
    • Basement – 1 Roof slab shuttering in progress.

March 2023 Report

  • A- BLOCK
    • Basement – 2 Slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 3 Slab shuttering in progress.

February 2023 Report

  • A- BLOCK
    • Basement – 3 Slab completed,
    • Basement – 2 walls & column casting in progress.
  • B- BLOCK
    • Basement – 3 Slab work in progress.

January 2023 Report

  • A block 1st slab completed second slab work in progress.
  • B block 1st slab completed second slab work in progress.