CONSTRUCTION UPDATES

1st September 2023 Report

  • A- BLOCK
    • First floor roof slab shuttering in progress.
  • B- BLOCK
    • Transfer slab Roof Reinforcement completed.

1st August 2023 Report

  • A- BLOCK
    • Clubhouse (Ground floor) slab Reinforcement work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

1st July 2023 Report

  • A- BLOCK
    • Ground floor walls concrete work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

1st June 2023 Report

  • A- BLOCK
    • Ground floor walls Reinforcement in progress.
  • B- BLOCK
    • Ground floor walls Reinforcement in progress.

1st May 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.

1st April 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab shuttering in progress.
  • B- BLOCK
    • Basement – 1 Roof slab shuttering in progress.

1st March 2023 Report

  • A- BLOCK
    • Basement – 2 Slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 3 Slab shuttering in progress.

1st February 2023 Report

  • A- BLOCK
    • Basement – 3 Slab completed,
    • Basement – 2 walls & column casting in progress.
  • B- BLOCK
    • Basement – 3 Slab work in progress.

1st January 2023 Report

  • A block 1st slab completed second slab work in progress.
  • B block 1st slab completed second slab work in progress.