Skip to content
TWINS
Project Status
CONSTRUCTION UPDATES
Previous
Next
1
st
March 2023 Report
A- BLOCK
Basement – 2 Slab Reinforcement in progress.
B- BLOCK
Basement – 3 Slab shuttering in progress.
Previous
Next
1
st
February 2023 Report
A- BLOCK
Basement – 3 Slab completed,
Basement – 2 walls & column casting in progress.
B- BLOCK
Basement – 3 Slab work in progress.
Previous
Next
1
st
January 2023 Report
A block 1st slab completed second slab work in progress.
B block 1st slab completed second slab work in progress.
Home
About Project
Amenities
Plan
Location
Project Status
Contact us
Menu
Home
About Project
Amenities
Plan
Location
Project Status
Contact us
Facebook
Instagram
Linkedin