CONSTRUCTION UPDATES

1st June 2024 Report

  • A- BLOCK
    • 08th floor Roof Slab work in progress.
  • B- BLOCK
    • 10th floor Roof Slab work in progress.
       

1st May 2024 Report

  • A- BLOCK
    • 07th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 08th floor Roof Reinforcement work in progress.
       

1st April 2024 Report

  • A- BLOCK
    • 06th floor Roof Reinforcement work in progress.
  • B- BLOCK
    • 07th floor Roof Reinforcement work in progress.

1st March 2024 Report

  • A- BLOCK
    • 05th floor Roof pour- 1 work in progress
  • B- BLOCK
    • 05th floor Roof pour- 1 work in progress, pour-2 completed.

1st February 2024 Report

  • A- BLOCK
    • Second floor Roof slab completed.
  • B- BLOCK
    • Third floor Roof slab completed.

1st January 2024 Report

  • A- BLOCK
    • Second floor Roof slab work in progress.
  • B- BLOCK
    • Second floor Roof slab work in progress.

1st December 2023 Report

  • A- BLOCK
    • Second floor slab Reinforcement in progress.
  • B- BLOCK
    • First floor slab Reinforcement in progress.

1st November 2023 Report

  • A- BLOCK
    • First floor roof slab. (Transfer slab concrete casting in progress).
  • B- BLOCK
    • Second Floor Roof slab (1st Mivan slab work in progress).

1st October 2023 Report

  • A- BLOCK
    • First floor roof slab. (Transfer slab level work in progress).
  • B- BLOCK
    • Transfer slab Roof slab, Typical level work in progress.

1st September 2023 Report

  • A- BLOCK
    • First floor roof slab shuttering in progress.
  • B- BLOCK
    • Transfer slab Roof Reinforcement completed.

1st August 2023 Report

  • A- BLOCK
    • Clubhouse (Ground floor) slab Reinforcement work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

1st July 2023 Report

  • A- BLOCK
    • Ground floor walls concrete work in progress.
  • B- BLOCK
    • Ground floor walls concrete work in progress.

1st June 2023 Report

  • A- BLOCK
    • Ground floor walls Reinforcement in progress.
  • B- BLOCK
    • Ground floor walls Reinforcement in progress.

1st May 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 1 Roof slab Reinforcement in progress.

1st April 2023 Report

  • A- BLOCK
    • Basement – 1 Roof slab shuttering in progress.
  • B- BLOCK
    • Basement – 1 Roof slab shuttering in progress.

1st March 2023 Report

  • A- BLOCK
    • Basement – 2 Slab Reinforcement in progress.
  • B- BLOCK
    • Basement – 3 Slab shuttering in progress.

1st February 2023 Report

  • A- BLOCK
    • Basement – 3 Slab completed,
    • Basement – 2 walls & column casting in progress.
  • B- BLOCK
    • Basement – 3 Slab work in progress.

1st January 2023 Report

  • A block 1st slab completed second slab work in progress.
  • B block 1st slab completed second slab work in progress.